Reconstruction of turbine foundation No. 3 & 5 at Neumünster Municipal PP

Turbine No.3 - Neumünster MPP
Turbine No.3 - Neumünster MPP

Spring elements released, turbine table back into the original position
Spring elements released, turbine table back into the original position

Alignment of spring elements
Alignment of spring elements

Turbine table supported on steel columns, concrete block cut out of the column
Turbine table supported on steel columns, concrete block cut out of the column

Removal of the previously cut concrete slab
Removal of the previously cut concrete slab

Diamond rope saw used to cut the columns
Diamond rope saw used to cut the columns

Original situation - settlements of approx. 6 cm
Original situation - settlements of approx. 6 cm

Original situation - settlements of approx. 6 cm
Original situation - settlements of approx. 6 cm

 


GERB Schwingungsisolierungen GmbH & Co. KG
Roedernallee 174-176, 13407 Berlin, Germany
Tel. +49-30-4191-0 | Fax +49-30-4191-199 | info-de(at)gerb.com

Project
Renovation of turbine foundation No. 3 & 5 at Neumünster Municipal Power Plant

Owner
Neumünster Municipal Power Plant, Germany

Problem
The foundation of Turbine No. 3 with a capacity of 25 MW had settled over the years by about 6 cm, although quite equally.


Measures taken
As a first step blocks of concrete corresponding to the height of the spring elements had to be cut out of each of the 6 columns to provide space for the installation of the spring elements. GERB organized a procedure to cut up to 38 cm high blocks out of the 1.2 x 1.2 m wide columns based on the use of a diamond rope saw. Only then it was possible to install spring elements in the structure of the originally rigid table type turbine foundation. Thereafter it was possible to realign the spring-supported system in an easy way on spring level. Later-on the same levelling procedure can be used at any time again and again as far as ever necessary.